Sign up to the MySalford newsletter and don't miss a thing happening in and around the city Roadworks around Salford precinct which were delayed due to Covid will cost 40 pc more than first agreed - with the local authority having to hand over an extra £1.2m.
The work on Hankinson Way, Rossall Way and the subways around Salford Shopping Centre started in September 2019 and were due to last 12 months.
But contractor Eurovia claims it has incurred extra costs needed to cover a drainage redesign, additional structural works to the subways and tackling Japanese Knotweed, taking the total price of the Pendleton project to £4.4m.
Read more on manchestereveningnews.co.uk
Get the latest stars news and celebrity rumours with exclusive stories, photos, videos and interviews.
Breaking up, scandals, engagements, divorces, gossip – all you need to know about the private lives of your favorite celebs.
Get to know the latest showbiz news along with exclusive interviews and even more. All this is waiting for you on the main page 24 hours a day, 7 days a week! Who, where, when, with whom, how, why and for what!? Stay tuned to know first!
Just follow us daily and we will provide you with the current news from the life of famous stars and celebrities.
Owner: SNOWLAND s.r.o.
Registration certificate 06691200
Address:
Snowland s.r.o.
16200, Na okraji 381/41, Veleslavín, 162 00 Praha 6
Czech Republic
©2024. All rights reserved.